Kavsak Bendi HEPP, Turkey
POST-TENSIONING SYSTEMS
Project:
Kavsak Bendi HEPP hydroelectric power plant, Turkey
Client:
Enerji SA
Construction period:
2012 - 2014
Construction company:
AGE Insaat ve Ticaret
Supplier:
ANP - Systems GmbH
Scope of supply:
SAS 950/1050 pre-stressing thread bars, diameter 36 mm. 284 bar tendons with bond.
Application:
ANP - Systems supplied, installed, stressed and grouted tendons. The tie back anchors transfer load congestion from the pivot points of the water weir into higher areas of the concrete structure. Tension load is 840 KN.